| Assessment Year | 1985 |
|---|---|
| Principal Product | DUST MOPS |
| NAICS |
n/a
|
| SIC | 2392: House furnishing, Except Curtains and Draperies |
| Sales Range | $5 M to 10M |
| # of Employees | 140 |
| Plant Area |
n/a
|
| Annual Production | 1,250,000
pieces
|
| Production Hrs. Annual | 2,250
hrs
|
| Location (State) | Kansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $27,357 | 417,644 |
kWh
|
$0.066 |
| Natural Gas | $11,217 | 2,920 |
MMBtu
|
$3.84 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $27,436 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $25,005 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2511: Insulate bare equipment | $1,719 | $500 |
$1,938
29,601
kWh
|
$(-219.0)
-
MMBtu
|
- | |
| 02 | 2.4322: Use or replace with energy efficient substitutes | $20,530 | $20,000 |
$595
9,086
kWh
|
$(-65.0)
-
MMBtu
|
$20,000 | |
| 03 | 2.2444: Use hot process fluids to preheat incoming process fluids | $799 | $1,500 | - |
$799
-
MMBtu
|
- | |
| 04 | 2.7111: Reduce illumination to minimum necessary levels | $1,842 | $2,505 |
$1,842
28,136
kWh
|
- | - | |
| 05 | 2.7261: Install timers and/or thermostats | $1,859 | $1,000 | - |
$1,859
-
MMBtu
|
- | |
| 06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $115 | - | - |
$215
-
MMBtu
|
$(-100.0) | |
| 07 | 2.1123: Install automatic stack damper | $572 | $1,000 | - |
$572
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $27,436 | $26,505 |
$4,375
66,823
kWh
|
$3,161
-
MMBtu
|
$19,900 | ||
| TOTAL IMPLEMENTED | $25,005 | $24,505 |
$4,375
66,823
kWh
|
$730
-
MMBtu
|
$19,900 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs