ITAC Assessment: KU0102
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1983
Principal Product TEMPERATURE SWITCHES
NAICS
n/a
SIC 3823: Industrial Instruments for Measurement, Display, and Control of Process Variables; and Related Products
Sales Range $5
M
to 10
M
# of Employees 82
Plant Area
n/a
Annual Production 50,000
pieces
Production Hrs. Annual 4,375
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $46,935 673,505
kWh
Natural Gas $18,272 3,460
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $5,215 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,213

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $612 $1,228 $612
8,792
kWh
-
02 2.3191: Use demand controller or load shedder $1,389 $4,000 $1,389
-
kWh
-
03 2.1233: Analyze flue gas for proper air/fuel ratio $1,241 $360 - $1,241
-
MMBtu
04 2.1123: Install automatic stack damper $824 $700 - $824
-
MMBtu
05 2.7261: Install timers and/or thermostats $808 $1,200 - $808
-
MMBtu
06 2.2532: Use only amount of air necessary to prevent explosion hazard $341 - $61
879
kWh
$280
-
MMBtu
TOTAL RECOMMENDED $5,215 $7,488 $2,062
9,671
kWh
$3,153
-
MMBtu
TOTAL IMPLEMENTED $2,213 $4,700 $1,389
-
kWh
$824
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs