ITAC Assessment: KU0096
ITAC logo
ITAC Assessment: KU0096
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1983
Principal Product ROLLER SKATES
NAICS
n/a
SIC 3949: Sporting and Athletic Goods, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 40
Plant Area
n/a
Annual Production 40,000
pieces
Production Hrs. Annual 2,268
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $10,221 138,042
kWh
Natural Gas $7,434 1,650
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $6,179 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7441: Replace broken windows and/or window sash $2,120 $189 - $2,120
-
MMBtu
02 2.7229: Air condition only space necessary $1,888 $5 $43
586
kWh
$1,845
-
MMBtu
03 2.7111: Reduce illumination to minimum necessary levels $999 $862 $999
13,482
kWh
-
04 2.2164: Turn off steam tracing during mild weather $225 - - $225
-
MMBtu
05 2.1123: Install automatic stack damper $420 $900 - $420
-
MMBtu
06 2.1231: Establish burner maintenance schedule for boilers $266 $480 - $266
-
MMBtu
07 2.6121: Reduce hot water temperature to the minimum required $261 - $261
3,517
kWh
-
TOTAL RECOMMENDED $6,179 $2,436 $1,303
17,585
kWh
$4,876
-
MMBtu
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs