ITAC Assessment: KU0078
ITAC logo
ITAC Assessment: KU0078
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1983
Principal Product HEET METAL TANKS
NAICS
n/a
SIC 3444: Sheet Metal Work
Sales Range $1
M
to 5
M
# of Employees 40
Plant Area
n/a
Annual Production 100
ton
Production Hrs. Annual 2,134
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $27,042 528,136
kWh
Natural Gas $14,355 4,029
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $6,902 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,207

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,695 $1,891 $1,695
33,118
kWh
-
02 2.7447: Install vinyl strip / high speed / air curtain doors $1,257 $167 - $1,257
-
MMBtu
03 2.4322: Use or replace with energy efficient substitutes $1,380 - $1,380
26,964
kWh
-
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,470 $78 $1,470
28,722
kWh
-
05 2.1123: Install automatic stack damper $1,100 $480 - $1,100
-
MMBtu
TOTAL RECOMMENDED $6,902 $2,616 $4,545
88,804
kWh
$2,357
-
MMBtu
TOTAL IMPLEMENTED $5,207 $725 $2,850
55,686
kWh
$2,357
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs