Assessment Year | 1982 |
---|---|
Principal Product | SPORTSWEAR |
NAICS |
n/a
|
SIC | 2329: Men's and Boys' Clothing, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 115 |
Plant Area |
n/a
|
Annual Production | 700,000
pieces
|
Production Hrs. Annual | 2,048
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $42,072 | 926,729 |
kWh
|
$0.045 |
Natural Gas | $16,105 | 4,386 |
MMBtu
|
$3.67 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $13,876 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,400 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,109 | $4,780 |
$2,109
46,600
kWh
|
- | |
02 | 2.7221: Lower temperature during the winter season and vice-versa | $6,254 | - |
$3,817
84,115
kWh
|
$2,437
-
MMBtu
|
|
03 | 2.7447: Install vinyl strip / high speed / air curtain doors | $973 | $139 |
$64
1,465
kWh
|
$909
-
MMBtu
|
|
04 | 2.3212: Optimize plant power factor | $1,623 | $2,350 |
$1,623
-
kWh
|
- | |
05 | 2.2511: Insulate bare equipment | $675 | $100 |
$537
11,723
kWh
|
$138
-
MMBtu
|
|
06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $420 | $400 | - |
$420
-
MMBtu
|
|
07 | 2.1123: Install automatic stack damper | $851 | $1,630 | - |
$851
-
MMBtu
|
|
08 | 2.7226: Use computer programs to optimize hvac performance | $798 | $950 |
$798
17,585
kWh
|
- | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $173 | $31 |
$173
3,810
kWh
|
- | |
TOTAL RECOMMENDED | $13,876 | $10,380 |
$9,121
165,298
kWh
|
$4,755
-
MMBtu
|
||
TOTAL IMPLEMENTED | $7,400 | $170 |
$4,054
89,390
kWh
|
$3,346
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs