Assessment Year | 1982 |
---|---|
Principal Product | ROUND PAPER CONTAINERS |
NAICS |
n/a
|
SIC | 2655: Fiber Cans, Tubes, Drums, and Similar Products |
Sales Range | $10 M to 50M |
# of Employees | 350 |
Plant Area |
n/a
|
Annual Production | 270,000
pieces
|
Production Hrs. Annual | 6,096
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $400,426 | 6,811,548 |
kWh
|
$0.059 |
Natural Gas | $93,655 | 29,965 |
MMBtu
|
$3.13 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $88,004 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $12,597 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,639 | $8,528 |
$11,639
198,124
kWh
|
- | |
02 | 2.4323: Use optimum size and capacity equipment | $20,021 | $5,480 |
$16,428
279,601
kWh
|
$3,593
-
MMBtu
|
|
03 | 2.3212: Optimize plant power factor | $15,210 | $7,760 |
$15,210
-
kWh
|
- | |
04 | 2.4239: Eliminate or reduce compressed air usage | $8,128 | $7,500 |
$8,128
138,335
kWh
|
- | |
05 | 2.7261: Install timers and/or thermostats | $6,755 | $6,659 | - |
$6,755
-
MMBtu
|
|
06 | 2.2444: Use hot process fluids to preheat incoming process fluids | $8,191 | $19,400 | - |
$8,191
-
MMBtu
|
|
07 | 2.2443: Re-use or recycle hot or cold process exhaust air | $5,136 | $8,125 | - |
$5,136
-
MMBtu
|
|
08 | 2.7447: Install vinyl strip / high speed / air curtain doors | $4,469 | $643 | - |
$4,469
-
MMBtu
|
|
09 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,891 | $150 | - |
$2,891
-
MMBtu
|
|
10 | 2.1123: Install automatic stack damper | $2,357 | $1,365 | - |
$2,357
-
MMBtu
|
|
11 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $2,002 | $882 |
$2,590
43,962
kWh
|
$(-588.0)
-
MMBtu
|
|
12 | 2.1224: Replace boiler | $1,205 | $3,200 | - |
$1,205
-
MMBtu
|
|
TOTAL RECOMMENDED | $88,004 | $69,692 |
$53,995
660,022
kWh
|
$34,009
-
MMBtu
|
||
TOTAL IMPLEMENTED | $12,597 | $8,143 |
$8,128
138,335
kWh
|
$4,469
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs