ITAC Assessment: KU0055
ITAC logo
ITAC Assessment: KU0055
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1982
Principal Product WALNUT GUNSTOCKS, LUMBER
NAICS
n/a
SIC 2426: Hardwood Dimension and Flooring Mills
Sales Range $1
M
to 5
M
# of Employees 52
Plant Area
n/a
Annual Production 2,700
thousand feet
Production Hrs. Annual 2,065
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $137,818 2,201,934
kWh
Natural Gas $6,767 2,336
MMBtu
Wood $184,272 198,092
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $127,340 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $17,854

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Wood Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $311 $520 $311
4,982
kWh
-
02 2.1233: Analyze flue gas for proper air/fuel ratio $28,915 $1,400 - $28,915
-
MMBtu
03 2.6126: Keep solid fuels / raw materials dry $14,171 - - $14,171
-
MMBtu
04 2.7441: Replace broken windows and/or window sash $15,482 $500 - $15,482
-
MMBtu
05 2.3212: Optimize plant power factor $2,061 $1,800 $2,061
-
kWh
-
06 2.3414: Burn waste to produce steam to drive a steam turbine generator set and use steam exhaust for heat $66,400 $240,000 $66,400
1,313,013
kWh
-
TOTAL RECOMMENDED $127,340 $244,220 $68,772
1,317,995
kWh
$58,568
-
MMBtu
TOTAL IMPLEMENTED $17,854 $2,820 $2,372
4,982
kWh
$15,482
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Wood Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs