ITAC Assessment: KU0049
ITAC logo
ITAC Assessment: KU0049
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1982
Principal Product PRINTING ON SPORTSWEAR
NAICS
n/a
SIC 2396: Automotive Trimmings, Apparel Findings, and Related Products
Sales Range $50
M
to 100
M
# of Employees 450
Plant Area
n/a
Annual Production 10,000,000
pieces
Production Hrs. Annual 4,428
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $268,093 4,817,995
kWh
Natural Gas $26,058 9,045
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $57,531 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $7,612 $3,222 $7,612
136,870
kWh
-
02 2.6222: Use drying oven (batch type) on alternate days or other optimum schedule to run equipment with full loads $42,700 - $42,700
767,878
kWh
-
03 2.7227: Use water on air conditioning exchanger to improve heat transfer and increase air conditioner efficiency $6,750 $6,900 $6,750
121,336
kWh
-
04 2.1123: Install automatic stack damper $399 $65 - $399
-
MMBtu
05 2.4221: Install compressor air intakes in coolest locations $70 $60 $70
1,172
kWh
-
TOTAL RECOMMENDED $57,531 $10,247 $57,132
1,027,256
kWh
$399
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs