Assessment Year | 1996 |
---|---|
Principal Product | commercial printing |
NAICS |
n/a
|
SIC | 2752: Commercial Printing, Lithographic |
Sales Range | $50 M to 100M |
# of Employees | 400 |
Plant Area |
188,000
ft2
|
Annual Production | 58,000,000
lb
|
Production Hrs. Annual | 8,700
hrs
|
Location (State) | Alabama |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $707,735 | 18,624,561 |
kWh
|
$0.038 |
Electricity Demand | $169,577 | 49,039 |
kW-mo/yr
|
$3.46 |
Electricity Fees | $140,214 | - |
|
- |
Natural Gas | $192,376 | 53,984 |
MMBtu
|
$3.56 |
LPG | $19,464 | 1,877 |
MMBtu
|
$10.37 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $189,164 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $139,231 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | LPG Savings | Other Liquid (haz) Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3137: Use power during off-peak periods | $10,089 | - | - |
$9,609
-
kW-mo/yr
|
$480 | - | - | - | |
02 | 2.3212: Optimize plant power factor | $33,556 | $59,500 | - |
$31,958
-
kW-mo/yr
|
$1,598 | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $11,120 | $700 |
$9,400
247,362
kWh
|
$1,190
-
kW-mo/yr
|
$530 | - | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $19,316 | $25,922 |
$16,104
423,798
kWh
|
$2,295
-
kW-mo/yr
|
$917 | - | - | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $21,363 | $74,200 |
$17,029
448,124
kWh
|
$3,278
-
kW-mo/yr
|
$1,056 | - | - | - | |
06 | 2.4226: Use / purchase optimum sized compressor | $4,520 | $9,000 |
$3,820
100,528
kWh
|
$477
-
kW-mo/yr
|
$223 | - | - | - | |
07 | 2.1332: Convert combustion equipment to burn natural gas | $12,700 | $27,000 | - | - | - |
$(-6,680.0)
-
MMBtu
|
$19,380
-
MMBtu
|
- | |
08 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $65,150 | $150,000 |
$70,966
1,867,526
kWh
|
$13,611
-
kW-mo/yr
|
$4,453 |
$(-23,880.0)
-
MMBtu
|
- | - | |
09 | 3.8141: Regenerate cleaning solvent on-site and reuse | $11,350 | $20,000 | - | - | - | - | - |
$11,350
-
gal
|
|
TOTAL RECOMMENDED | $189,164 | $366,322 |
$117,319
3,087,338
kWh
|
$62,418
-
kW-mo/yr
|
$9,257 |
$(-30,560.0)
-
MMBtu
|
$19,380
-
MMBtu
|
$11,350
-
gal
|
||
TOTAL IMPLEMENTED | $139,231 | $236,122 |
$96,470
2,538,686
kWh
|
$58,663
-
kW-mo/yr
|
$7,978 |
$(-23,880.0)
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | LPG Savings | Other Liquid (haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs