Assessment Year | 2022 |
---|---|
Principal Product | Treated Fibers |
NAICS | 314999: All Other Miscellaneous Textile Product Mills |
SIC | 2299: Textile goods, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 50 |
Plant Area |
154,634
ft2
|
Annual Production | 25,699,286
lb
|
Production Hrs. Annual | 8,000
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $335,342 | 4,312,600 |
kWh
|
$0.078 | |
Electricity Demand | $56,699 | 16,925 |
kW-mo/yr
|
$3.35 | |
Electricity Fees | $1,800 | - |
|
- | |
Natural Gas | $559,947 | 85,462 |
MMBtu
|
$6.55 | |
Waste Disposal Costs | |||||
Water Usage | $279,695 | 94,656 |
Tgal
|
$2.95 | |
Water Disposal | $307,181 | 94,656 |
Tgal
|
$3.25 | |
TOTAL YEARLY COSTS | $1,540,664 | ||||
RECOMMENDED SAVINGS* | $178,497 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $140,578 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2136: Install / repair insulation on steam lines | $6,958 | $5,101 | - | - |
$6,958
-
MMBtu
|
- | - | |
02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,131 | - | - | - |
$4,251
-
MMBtu
|
$(-3,120.0) | - | |
03 | 2.2414: Use waste heat from hot flue gases to preheat | $27,117 | $60,601 | - | - |
$27,117
-
MMBtu
|
- | - | |
04 | 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat | $98,216 | $570,000 |
$122,880
1,600,000
kWh
|
$8,040
-
kW-mo/yr
|
$(-26,304.0)
-
MMBtu
|
- | $(-6,400.0) | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $18,656 | $5,480 |
$17,510
228,000
kWh
|
$1,146
-
kW-mo/yr
|
- | - | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,676 | $45 |
$1,573
20,483
kWh
|
$103
-
kW-mo/yr
|
- | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,941 | $13,595 |
$11,416
148,640
kWh
|
$747
-
kW-mo/yr
|
- | - | $1,778 | |
08 | 2.4133: Use most efficient type of electric motors | $10,802 | $59,793 |
$9,891
128,795
kWh
|
$911
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $178,497 | $714,615 |
$163,270
2,125,918
kWh
|
$10,947
-
kW-mo/yr
|
$12,022
-
MMBtu
|
$(-3,120.0) | $(-4,622.0) | ||
TOTAL IMPLEMENTED | $140,578 | $594,221 |
$153,379
1,997,123
kWh
|
$10,036
-
kW-mo/yr
|
$(-15,095.0)
-
MMBtu
|
$(-3,120.0) | $(-4,622.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs