Assessment Year | 1997 |
---|---|
Principal Product | Children's apparel |
NAICS |
n/a
|
SIC | 2380: |
Sales Range | $50 M to 100M |
# of Employees | 365 |
Plant Area |
108,000
ft2
|
Annual Production | 14,400,000
pieces
|
Production Hrs. Annual | 2,125
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $108,800 | 2,021,395 |
kWh
|
$0.054 |
Electricity Demand | $22,824 | 8,157 |
kW-mo/yr
|
$2.80 |
Electricity Fees | $5,643 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $271,070 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $7,457 | $3,000 | n/a |
$7,457
140,680
kWh
|
- | - | - |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,185 | $2,412 | n/a |
$3,615
68,288
kWh
|
$570
-
kW-mo/yr
|
- | - |
03 | 2.4133: Use most efficient type of electric motors | $885 | $1,620 | n/a |
$820
15,533
kWh
|
$65
-
kW-mo/yr
|
- | - |
04 | 3.5313: Increase amount of waste recovered for resale | $4,140 | $1,025 | n/a | - | - |
$4,140
-
lb
|
- |
05 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $5,063 | - | n/a | - | - |
$5,063
-
lb
|
- |
06 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $1,708 | - | n/a | - | - |
$1,708
-
lb
|
- |
07 | 4.441: Install automatic packing equipment | $247,632 | $45,000 | n/a | - | - | - | $247,632 |
TOTAL RECOMMENDED | $271,070 | $53,057 |
$11,892
224,501
kWh
|
$635
-
kW-mo/yr
|
$10,911
-
lb
|
$247,632 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs