Assessment Year | 1996 |
---|---|
Principal Product | Electric and non electric detonators |
NAICS |
n/a
|
SIC | 2892: Explosives |
Sales Range | $10 M to 50M |
# of Employees | 26 |
Plant Area |
24,000
ft2
|
Annual Production | 1,096,000,000
thousand feet
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $67,057 | 1,184,642 |
kWh
|
$0.057 |
Electricity Demand | $5,995 | 1,874 |
kW-mo/yr
|
$3.20 |
Electricity Fees | $2,944 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $39,144 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,932 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7221: Lower temperature during the winter season and vice-versa | $6,148 | - |
$6,148
126,026
kWh
|
- | - | - | |
02 | 2.7221: Lower temperature during the winter season and vice-versa | $3,206 | - |
$3,206
65,651
kWh
|
- | - | - | |
03 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $3,396 | $1,500 |
$3,396
34,877
kWh
|
- | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,330 | $25 |
$1,216
24,912
kWh
|
$114
-
kW-mo/yr
|
- | - | |
05 | 2.4133: Use most efficient type of electric motors | $1,255 | $1,900 |
$1,160
23,740
kWh
|
$95
-
kW-mo/yr
|
- | - | |
06 | 2.7261: Install timers and/or thermostats | $966 | $150 |
$966
19,930
kWh
|
- | - | - | |
07 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $955 | - | - | - | $955 | - | |
08 | 3.1192: Reduce scrap production | $21,888 | $2,000 | - | - | - |
$21,888
-
lb
|
|
TOTAL RECOMMENDED | $39,144 | $5,575 |
$16,092
295,136
kWh
|
$209
-
kW-mo/yr
|
$955 |
$21,888
-
lb
|
||
TOTAL IMPLEMENTED | $7,932 | $1,525 |
$7,818
125,440
kWh
|
$114
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs