| Assessment Year | 2021 |
|---|---|
| Principal Product | Machined Parts |
| NAICS | 332710: Machine Shops |
| SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 190 |
| Plant Area |
57,500
ft2
|
| Annual Production | 1,000,000
units
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $491,731 | 4,351,968 |
kWh
|
$0.11 |
| Electricity Demand | $293,114 | 8,465 |
kW-mo/yr
|
$34.63 |
| Natural Gas | $1,893 | 134 |
MMBtu
|
$14.13 |
| TOTAL YEARLY COSTS | $786,738 | |||
| RECOMMENDED SAVINGS* | $128,102 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $56,790 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.6218: Turn off equipment when not in use | $40,609 | - |
$40,609
298,818
kWh
|
- | - | - | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $12,914 | - |
$14,514
106,810
kWh
|
- | $(-1,600.0) | - | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,183 | $400 |
$3,073
22,608
kWh
|
$1,110
-
kW-mo/yr
|
- | - | |
| 04 | 2.7243: Improve air circulation with destratification fans / other methods | $2,048 | $860 |
$1,491
10,972
kWh
|
$557
-
kW-mo/yr
|
- | - | |
| 05 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $26,520 | $43,936 |
$26,520
195,146
kWh
|
- | - | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $41,828 | $70,690 |
$23,217
170,836
kWh
|
$13,200
-
kW-mo/yr
|
- | $5,411 | |
| TOTAL RECOMMENDED | $128,102 | $115,886 |
$109,424
805,190
kWh
|
$14,867
-
kW-mo/yr
|
$(-1,600.0) | $5,411 | ||
| TOTAL IMPLEMENTED | $56,790 | $71,550 |
$39,222
288,618
kWh
|
$13,757
-
kW-mo/yr
|
$(-1,600.0) | $5,411 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs