ITAC Assessment: SF0444
ITAC logo
ITAC Assessment: SF0444
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Metal Heat Treating
NAICS 332811: Metal Heat Treating
SIC 3398: Metal Heat Treating
Sales Range $10
M
to 50
M
# of Employees 31
Plant Area 37,000
ft2
Annual Production 0
units
Production Hrs. Annual 6,968
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $184,432 1,931,019
kWh
Electricity Demand $57,154 8,271
kW-mo/yr
Natural Gas $197,223 29,578
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $29,528 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $404

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Ancillary Material Cost Savings
01 2.2443: Re-use or recycle hot or cold process exhaust air $9,479 $8,763 $186
1,949
kWh
$9,293
-
MMBtu
-
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $3,108 $4,124 $3,108
32,542
kWh
- -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $7,895 $22,758 $7,895
82,666
kWh
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $404 $1,967 $201
2,107
kWh
- $203
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $8,642 $40,100 $8,642
90,486
kWh
- -
TOTAL RECOMMENDED $29,528 $77,712 $20,032
209,750
kWh
$9,293
-
MMBtu
$203
TOTAL IMPLEMENTED $404 $1,967 $201
2,107
kWh
- $203
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs