ITAC Assessment: KG0055
ITAC logo
ITAC Assessment: KG0055
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Fresh Packaged Shrimp
NAICS
n/a
SIC 2092: Prepared Fresh or Frozen Fish and Seafoods
Sales Range $1
M
to 5
M
# of Employees 20
Plant Area 75,000
ft2
Annual Production 11,000,000
lb
Production Hrs. Annual 2,600
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $78,362 980,363
kWh
Electricity Fees $2,164 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $35,813 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $24,954

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Water Disposal Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Ancillary Material Cost Savings
01 2.8114: Change rate schedules or other changes in utility service $5,631 - - - - - $5,631
02 2.2626: Avoid frost formation on evaporators $6,153 - $6,153
121,043
kWh
- - - -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $7,832 $3,600 $7,832
70,926
kWh
- - - -
04 2.4133: Use most efficient type of electric motors $4,962 $10,860 $4,962
44,842
kWh
- - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,309 $212 $1,309
12,016
kWh
- - - -
06 2.7135: Install occupancy sensors $664 $130 $664
6,155
kWh
- - - -
07 2.7261: Install timers and/or thermostats $2,189 $450 $2,189
19,930
kWh
- - - -
08 3.3122: Use filtration, centrifuging to remove contaminants $2,015 $975 - - $2,015
-
gal
- -
09 3.3122: Use filtration, centrifuging to remove contaminants $4,004 $2,930 - $4,004
-
Tgal
- - -
10 3.5311: Recover and reuse waste material $1,054 - - - - $1,054
-
lb
-
TOTAL RECOMMENDED $35,813 $19,157 $23,109
274,912
kWh
$4,004
-
Tgal
$2,015
-
gal
$1,054
-
lb
$5,631
TOTAL IMPLEMENTED $24,954 $15,215 $13,304
185,815
kWh
$4,004
-
Tgal
$2,015
-
gal
- $5,631
Yearly Savings* Imp'd Cost* Electricity Usage Savings Water Disposal Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs