Assessment Year | 1996 |
---|---|
Principal Product | Shrimp Processing |
NAICS |
n/a
|
SIC | 2092: Prepared Fresh or Frozen Fish and Seafoods |
Sales Range | $1 M to 5M |
# of Employees | 170 |
Plant Area |
65,522
ft2
|
Annual Production | 12,000,000
lb
|
Production Hrs. Annual | 2,600
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $127,689 | 5,064,185 |
kWh
|
$0.025 |
Electricity Demand | $156,075 | 11,544 |
kW-mo/yr
|
$13.52 |
Electricity Fees | $4,655 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $126,578 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $37,697 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $16,108 | $13,600 |
$4,724
182,298
kWh
|
$11,384
-
kW-mo/yr
|
- | - | |
02 | 2.2696: Use excess cold process fluid for industrial cooling needs | $12,871 | $6,433 |
$12,871
109,906
kWh
|
- | - | - | |
03 | 2.4133: Use most efficient type of electric motors | $7,070 | $22,830 |
$2,680
103,458
kWh
|
$4,390
-
kW-mo/yr
|
- | - | |
04 | 2.2511: Insulate bare equipment | $1,525 | $18,000 |
$1,525
34,291
kWh
|
- | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,099 | $361 |
$320
12,309
kWh
|
$779
-
kW-mo/yr
|
- | - | |
06 | 2.7261: Install timers and/or thermostats | $363 | $450 |
$363
14,068
kWh
|
- | - | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $178 | $20 |
$52
879
kWh
|
$126
-
kW-mo/yr
|
- | - | |
08 | 3.3122: Use filtration, centrifuging to remove contaminants | $73,944 | $22,000 | - | - |
$73,944
-
Tgal
|
- | |
09 | 3.5311: Recover and reuse waste material | $13,420 | - | - | - | - |
$13,420
-
lb
|
|
TOTAL RECOMMENDED | $126,578 | $83,694 |
$22,535
457,209
kWh
|
$16,679
-
kW-mo/yr
|
$73,944
-
Tgal
|
$13,420
-
lb
|
||
TOTAL IMPLEMENTED | $37,697 | $36,791 |
$7,724
298,065
kWh
|
$16,553
-
kW-mo/yr
|
- |
$13,420
-
lb
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs