ITAC Assessment: KG0040
ITAC logo
ITAC Assessment: KG0040
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Prestressed Concrete Members
NAICS
n/a
SIC 3272: Concrete Products, Except Block and Brick
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area 51,553
ft2
Annual Production 1,000
units
Production Hrs. Annual 2,080
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $72,632 649,472
kWh
Natural Gas $23,407 7,517
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $16,344 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,824

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4133: Use most efficient type of electric motors $8,768 $8,330 $8,768
63,306
kWh
02 2.4314: Use synthetic lubricant $2,520 - $2,520
16,120
kWh
03 2.7261: Install timers and/or thermostats $3,469 $900 $3,469
35,170
kWh
04 2.4231: Reduce the pressure of compressed air to the minimum required $937 $20 $937
5,862
kWh
05 2.7135: Install occupancy sensors $650 $195 $650
6,741
kWh
TOTAL RECOMMENDED $16,344 $9,445 $16,344
127,199
kWh
TOTAL IMPLEMENTED $13,824 $9,445 $13,824
111,079
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs