ITAC Assessment: KG0008
ITAC logo
ITAC Assessment: KG0008
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Variety Bread
NAICS
n/a
SIC 2051: Bread and Other Bakery Products, Except Cookies and Crackers
Sales Range $10
M
to 50
M
# of Employees 306
Plant Area 107,127
ft2
Annual Production 62,400,000
lb
Production Hrs. Annual 8,736
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $572,055 10,905,041
kWh
Natural Gas $343,279 80,919
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $19,465 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $18,940

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4133: Use most efficient type of electric motors $11,284 $21,400 $11,284
265,826
kWh
02 2.4231: Reduce the pressure of compressed air to the minimum required $5,308 $1,770 $5,308
112,544
kWh
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,261 $389 $1,261
44,256
kWh
04 2.7261: Install timers and/or thermostats $1,087 $450 $1,087
37,808
kWh
05 2.7135: Install occupancy sensors $418 $260 $418
14,654
kWh
06 2.7142: Utilize higher efficiency lamps and/or ballasts $107 $450 $107
2,345
kWh
TOTAL RECOMMENDED $19,465 $24,719 $19,465
477,433
kWh
TOTAL IMPLEMENTED $18,940 $24,009 $18,940
460,434
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs