| Assessment Year | 2026 |
|---|---|
| Principal Product | Corrugated and Solid Fiber Boxes |
| NAICS | 322211: Corrugated and Solid Fiber Box Manufacturing |
| SIC | 2653: Corrugated and Solid Fiber Boxes |
| Sales Range | $50 M to 100M |
| # of Employees | 300 |
| Plant Area |
550,000
ft2
|
| Annual Production | 960,000
thousand feet
|
| Production Hrs. Annual | 6,864
hrs
|
| Location (State) | Indiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $697,705 | 13,236,101 |
kWh
|
$0.053 | |
| Electricity Demand | $530,422 | 27,314 |
kW-mo/yr
|
$19.42 | |
| Electricity Fees | $244,369 | - |
|
- | |
| Natural Gas | $619,228 | 75,828 |
MMBtu
|
$8.17 | |
| Waste Disposal Costs | |||||
| Water Usage | $65,675 | 12,239 |
Tgal
|
$5.37 | |
| TOTAL YEARLY COSTS | $2,157,399 | ||||
| RECOMMENDED SAVINGS* | $96,921 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $18,392 | - |
$12,246
231,050
kWh
|
$6,146
-
kW-mo/yr
|
- | - | |
| 02 | 2.7224: Reduce space conditioning during non-working hours | $2,359 | - | - | - |
$2,359
-
MMBtu
|
- | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $22,280 | $2,784 |
$14,834
279,882
kWh
|
$7,446
-
kW-mo/yr
|
- | - | |
| 04 | 2.3212: Optimize plant power factor | $32,045 | $48,160 | - | - | - | $32,045 | |
| 05 | 2.2414: Use waste heat from hot flue gases to preheat | $19,126 | $49,500 | - | - |
$19,126
-
MMBtu
|
- | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,719 | $9,213 |
$1,657
31,272
kWh
|
$1,062
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $96,921 | $109,657 |
$28,737
542,204
kWh
|
$14,654
-
kW-mo/yr
|
$21,485
-
MMBtu
|
$32,045 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs