ITAC Assessment: IP0213
ITAC logo
ITAC Assessment: IP0213
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Metal Plating
NAICS 332813: Electroplating, Plating, Polishing, Anodizing, and Coloring
SIC 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring
Sales Range $5
M
to 10
M
# of Employees 45
Plant Area 33,149
ft2
Annual Production 4,740,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $321,832 2,420,480
kWh
Natural Gas $175,610 20,736
MMBtu
Waste Disposal Costs
Water Usage $22,689 7,559
Tgal
Water Disposal $91,247 7,559
Tgal
TOTAL YEARLY COSTS $611,378
RECOMMENDED SAVINGS* $158,635 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4221: Install compressor air intakes in coolest locations $1,494 - $1,494
11,232
kWh
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $15,623 $640 $15,623
117,465
kWh
-
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $10,374 $270 $10,374
78,000
kWh
-
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $40,943 $4,528 $40,943
307,840
kWh
-
05 2.7135: Install occupancy sensors $953 $280 $953
7,169
kWh
-
06 2.4324: Replace hydraulic / pneumatic equipment with electric equipment $9,346 $3,710 $9,346
70,268
kWh
-
07 2.7224: Reduce space conditioning during non-working hours $825 $340 $495
3,720
kWh
$330
-
MMBtu
08 2.1243: Use heat from boiler blowdown to preheat boiler feed water $48,428 $56,200 - $48,428
-
MMBtu
09 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $23,151 $26,250 $23,151
174,068
kWh
-
10 2.7142: Utilize higher efficiency lamps and/or ballasts $7,498 $13,433 $7,498
56,374
kWh
-
TOTAL RECOMMENDED $158,635 $105,651 $109,877
826,136
kWh
$48,758
-
MMBtu
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs