Assessment Year | 2004 |
---|---|
Principal Product | Steering Column |
NAICS | 336330: Motor Vehicle Steering and Suspension Components (except Spring) Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $50 M to 100M |
# of Employees | 140 |
Plant Area |
39,500
ft2
|
Annual Production | 650,000
pieces
|
Production Hrs. Annual | 4,250
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $103,182 | 1,102,840 |
kWh
|
$0.094 |
Electricity Demand | $1,118 | 327 |
kW-mo/yr
|
$3.42 |
Electricity Fees | $1,957 | - |
|
- |
Natural Gas | $15,263 | 2,075 |
MMBtu
|
$7.36 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $34,830 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $13,526 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 3.5218: Reuse / recycle/ sell rubber products | $16,200 | $400 | - | - | - | $16,200 | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,256 | $975 |
$8,224
106,866
kWh
|
$1,032
-
kW-mo/yr
|
- | - | |
03 | 2.7243: Improve air circulation with destratification fans / other methods | $4,423 | $2,450 | - | - |
$4,423
-
MMBtu
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,373 | $3,897 |
$3,027
39,330
kWh
|
$346
-
kW-mo/yr
|
- | - | |
05 | 2.4237: Substitute compressed air cooling with water or air cooling | $897 | $420 |
$797
10,355
kWh
|
$100
-
kW-mo/yr
|
- | - | |
06 | 2.4239: Eliminate or reduce compressed air usage | $681 | $1,000 |
$605
7,858
kWh
|
$76
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $34,830 | $9,142 |
$12,653
164,409
kWh
|
$1,554
-
kW-mo/yr
|
$4,423
-
MMBtu
|
$16,200 | ||
TOTAL IMPLEMENTED | $13,526 | $5,292 |
$12,048
156,551
kWh
|
$1,478
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs