Assessment Year | 2025 |
---|---|
Principal Product | Steel Casting |
NAICS | 331513: Steel Foundries (except Investment) |
SIC | 3325: Steel Foundries, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 445 |
Plant Area |
682,381
ft2
|
Annual Production | 10,000
ton
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,531,218 | 34,864,713 |
kWh
|
$0.073 |
Electricity Demand | $518,742 | 124,512 |
kW-mo/yr
|
$4.17 |
Electricity Fees | $(-133,074.0) | - |
|
- |
Natural Gas | $894,040 | 236,520 |
MMBtu
|
$3.78 |
TOTAL YEARLY COSTS | $3,810,926 | |||
RECOMMENDED SAVINGS* | $185,352 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4239: Eliminate or reduce compressed air usage | $35,159 | - |
$28,620
392,049
kWh
|
$6,539
-
kW-mo/yr
|
- | |
02 | 2.6218: Turn off equipment when not in use | $21,763 | - |
$21,763
298,125
kWh
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $16,693 | $523 |
$14,983
205,250
kWh
|
$1,710
-
kW-mo/yr
|
- | |
04 | 2.7243: Improve air circulation with destratification fans / other methods | $27,000 | $2,636 |
$21,979
301,080
kWh
|
$5,021
-
kW-mo/yr
|
- | |
05 | 2.4221: Install compressor air intakes in coolest locations | $1,100 | $872 |
$1,100
15,060
kWh
|
- | - | |
06 | 2.2437: Recover waste heat from equipment | $46,331 | $50,406 | - | - |
$46,331
-
MMBtu
|
|
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,645 | $7,496 |
$5,065
69,379
kWh
|
$580
-
kW-mo/yr
|
- | |
08 | 2.4133: Use most efficient type of electric motors | $30,273 | $56,876 |
$27,371
374,940
kWh
|
$2,902
-
kW-mo/yr
|
- | |
09 | 2.7135: Install occupancy sensors | $1,388 | $3,150 |
$1,388
19,008
kWh
|
- | - | |
TOTAL RECOMMENDED | $185,352 | $121,959 |
$122,269
1,674,891
kWh
|
$16,752
-
kW-mo/yr
|
$46,331
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs