| Assessment Year | 2024 |
|---|---|
| Principal Product | Athletic Equipment |
| NAICS | 339920: Sporting and Athletic Goods Manufacturing |
| SIC | 3949: Sporting and Athletic Goods, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 150 |
| Plant Area |
200,000
ft2
|
| Annual Production | 903,185
pieces
|
| Production Hrs. Annual | 4,394
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $154,978 | 1,809,074 |
kWh
|
$0.086 | |
| Electricity Demand | $45,343 | 5,879 |
kW-mo/yr
|
$7.71 | |
| Electricity Fees | $15,536 | - |
|
- | |
| Natural Gas | $109,235 | 25,494 |
MMBtu
|
$4.28 | |
| Waste Disposal Costs | |||||
| Water Usage | $24,873 | 2,627 |
Tgal
|
$9.47 | |
| TOTAL YEARLY COSTS | $349,965 | ||||
| RECOMMENDED SAVINGS* | $4,393 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $2,758 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.6218: Turn off equipment when not in use | $108 | - |
$108
1,260
kWh
|
- | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $564 | $170 |
$564
6,556
kWh
|
- | |
| 03 | 2.7135: Install occupancy sensors | $447 | $356 |
$447
5,196
kWh
|
- | |
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $534 | $585 |
$257
2,990
kWh
|
$277
-
kW-mo/yr
|
|
| 05 | 2.4221: Install compressor air intakes in coolest locations | $1,101 | $1,322 |
$867
10,080
kWh
|
$234
-
kW-mo/yr
|
|
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,639 | $3,266 |
$1,317
15,312
kWh
|
$322
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $4,393 | $5,699 |
$3,560
41,394
kWh
|
$833
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $2,758 | $3,792 |
$2,436
28,324
kWh
|
$322
-
kW-mo/yr
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs