Assessment Year | 2023 |
---|---|
Principal Product | Musical Instruments |
NAICS | 339992: Musical Instrument Manufacturing |
SIC | 3931: Musical Instruments |
Sales Range | $10 M to 50M |
# of Employees | 130 |
Plant Area |
75,868
ft2
|
Annual Production | 2,200
units
|
Production Hrs. Annual | 3,981
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $111,719 | 1,604,972 |
kWh
|
$0.070 | |
Electricity Fees | $3,247 | - |
|
- | |
Natural Gas | $19,641 | 2,190 |
MMBtu
|
$8.97 | |
Waste Disposal Costs | |||||
Water Usage | $36,325 | 179,028 |
Tgal
|
$0.20 | |
TOTAL YEARLY COSTS | $170,932 | ||||
RECOMMENDED SAVINGS* | $16,382 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $9,397 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,649 | $1,428 |
$4,649
66,414
kWh
|
- | |
02 | 2.7243: Improve air circulation with destratification fans / other methods | $4,853 | $2,064 |
$2,004
25,047
kWh
|
$2,849
-
MMBtu
|
|
03 | 2.7492: Use proper thickness of insulation on building envelope | $1,643 | $1,028 |
$103
1,465
kWh
|
$1,540
-
MMBtu
|
|
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,851 | $1,271 |
$1,851
26,439
kWh
|
- | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,709 | $1,228 |
$1,709
24,414
kWh
|
- | |
06 | 2.2437: Recover waste heat from equipment | $972 | $1,279 | - |
$972
-
MMBtu
|
|
07 | 2.4221: Install compressor air intakes in coolest locations | $216 | $803 |
$216
3,084
kWh
|
- | |
08 | 2.7243: Improve air circulation with destratification fans / other methods | $489 | $2,128 |
$13
442
kWh
|
$476
-
MMBtu
|
|
TOTAL RECOMMENDED | $16,382 | $11,229 |
$10,545
147,305
kWh
|
$5,837
-
MMBtu
|
||
TOTAL IMPLEMENTED | $9,397 | $6,009 |
$8,425
120,351
kWh
|
$972
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs