Assessment Year | 2022 |
---|---|
Principal Product | Machined parts and PEO coated parts |
NAICS | 332813: Electroplating, Plating, Polishing, Anodizing, and Coloring |
SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
Sales Range | $5 M to 10M |
# of Employees | 47 |
Plant Area |
42,666
ft2
|
Annual Production | 4,680
pieces
|
Production Hrs. Annual | 4,940
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $129,784 | 4,456,483 |
kWh
|
$0.029 | |
Electricity Demand | $294,322 | 13,362 |
kW-mo/yr
|
$22.03 | |
Electricity Fees | $5,740 | - |
|
- | |
Natural Gas | $12,767 | 1,625 |
MMBtu
|
$7.86 | |
Waste Disposal Costs | |||||
Water Usage | $8,463 | 1,394 |
Tgal
|
$6.07 | |
TOTAL YEARLY COSTS | $451,076 | ||||
RECOMMENDED SAVINGS* | $3,865 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
---|---|---|---|---|---|---|---|
01 | 4.821: Pay bills on time to avoid late fees | $197 | - | - | - | $197 | |
02 | 2.8121: Apply for tax-free status for energy purchases | $3,276 | $5,000 | - | - | $3,276 | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $10 | $22 |
$1
33
kWh
|
$9
-
kW-mo/yr
|
- | |
04 | 2.4221: Install compressor air intakes in coolest locations | $382 | $865 |
$78
2,691
kWh
|
$304
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $3,865 | $5,887 |
$79
2,724
kWh
|
$313
-
kW-mo/yr
|
$3,473 | ||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs