Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product Wastewater
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range $1
M
to 5
M
# of Employees 22
Plant Area 1,001,880
ft2
Annual Production 947,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $88,246 2,660,000
kWh
Electricity Demand $130,164 5,016
kW-mo/yr
Electricity Fees $619 -
Natural Gas $19,032 3,614
MMBtu
TOTAL YEARLY COSTS $238,061
RECOMMENDED SAVINGS* $4,022 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,022

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.2691: Shut off cooling if cold outside air will cool process $1,898 $1,950 $1,898
57,204
kWh
-
02 2.4157: Establish a predictive maintenance program $188 $500 $91
2,738
kWh
$97
-
kW-mo/yr
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,936 $6,650 $1,132
34,117
kWh
$804
-
kW-mo/yr
TOTAL RECOMMENDED $4,022 $9,100 $3,121
94,059
kWh
$901
-
kW-mo/yr
TOTAL IMPLEMENTED $4,022 $9,100 $3,121
94,059
kWh
$901
-
kW-mo/yr
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs