ITAC Assessment: CI0055
ITAC logo
ITAC Assessment: CI0055
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Ready Mix Concrete
NAICS 327320: Ready-Mix Concrete Manufacturing
SIC 3273: Ready-Mixed Concrete
Sales Range $1
M
to 5
M
# of Employees 31
Plant Area 88,180
ft2
Annual Production 274,054
units
Production Hrs. Annual 7,488
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $127,886 762,000
kWh
Electricity Demand $55,193 3,931
kW-mo/yr
Electricity Fees $24,273 -
Waste Disposal Costs
Water Usage $132,307 9,445
Tgal
Water Disposal $17,549 9,445
Tgal
TOTAL YEARLY COSTS $357,208
RECOMMENDED SAVINGS* $98,558 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings One-time Revenue or Avoided Cost Savings
01 2.9114: Use solar heat to make electricty $47,726 $259,574 $42,793
255,028
kWh
$4,933
-
kW-mo/yr
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $17,837 $4,300 $16,339
97,371
kWh
$1,498
-
kW-mo/yr
-
03 2.4133: Use most efficient type of electric motors $15,348 $4,370 $13,526
80,606
kWh
$1,822
-
kW-mo/yr
-
04 2.3141: Use battery storage for demand control $14,647 $22,685 $3,609
21,509
kWh
$11,038
-
kW-mo/yr
-
05 4.651: Install back-up equipment $3,000 $300 - - $3,000
TOTAL RECOMMENDED $98,558 $291,229 $76,267
454,514
kWh
$19,291
-
kW-mo/yr
$3,000
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs