Assessment Year | 2018 |
---|---|
Principal Product | Metal Plating |
NAICS | 332813: Electroplating, Plating, Polishing, Anodizing, and Coloring |
SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
Sales Range | $10 M to 50M |
# of Employees | 68 |
Plant Area |
50,000
ft2
|
Annual Production | 300,000,000
pieces
|
Production Hrs. Annual | 6,120
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $125,836 | 3,845,160 |
kWh
|
$0.033 |
Electricity Demand | $218,709 | 8,392 |
kW-mo/yr
|
$26.06 |
Electricity Fees | $1,055 | - |
|
- |
Natural Gas | $42,338 | 6,030 |
MMBtu
|
$7.02 |
TOTAL YEARLY COSTS | $387,938 | |||
RECOMMENDED SAVINGS* | $15,960 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,439 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7221: Lower temperature during the winter season and vice-versa | $1,378 | - |
$185
5,650
kWh
|
- |
$1,193
-
MMBtu
|
|
02 | 2.4322: Use or replace with energy efficient substitutes | $767 | - |
$298
9,119
kWh
|
$469
-
kW-mo/yr
|
- | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $780 | $217 |
$373
11,406
kWh
|
$407
-
kW-mo/yr
|
- | |
04 | 2.7135: Install occupancy sensors | $1,101 | $893 |
$1,101
33,626
kWh
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,069 | $26,837 |
$3,710
113,341
kWh
|
$6,359
-
kW-mo/yr
|
- | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $280 | $801 |
$280
8,546
kWh
|
- | - | |
07 | 2.4322: Use or replace with energy efficient substitutes | $95 | $295 |
$95
2,892
kWh
|
- | - | |
08 | 2.4239: Eliminate or reduce compressed air usage | $1,310 | $4,238 |
$1,310
40,029
kWh
|
- | - | |
09 | 2.4221: Install compressor air intakes in coolest locations | $180 | $679 |
$86
2,628
kWh
|
$94
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $15,960 | $33,960 |
$7,438
227,237
kWh
|
$7,329
-
kW-mo/yr
|
$1,193
-
MMBtu
|
||
TOTAL IMPLEMENTED | $3,439 | $1,789 |
$1,745
53,310
kWh
|
$501
-
kW-mo/yr
|
$1,193
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs