ITAC Assessment: IP0084
ITAC logo
ITAC Assessment: IP0084
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Steel/Alloy casting for bearing manufacturing
NAICS 336310: Motor Vehicle Gasoline Engine and Engine Parts Manufacturing
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $10
M
to 50
M
# of Employees 31
Plant Area 110,950
ft2
Annual Production 5,100,000
lb
Production Hrs. Annual 4,800
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $271,718 7,010,894
kWh
Electricity Demand $335,160 22,344
kW-mo/yr
Electricity Fees $76,520 -
Natural Gas $74,720 12,483
MMBtu
Waste Disposal Costs
Water Usage $4,557 115,550
Tgal
TOTAL YEARLY COSTS $762,675
RECOMMENDED SAVINGS* $37,805 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $18,718

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Usage Savings
01 2.4323: Use optimum size and capacity equipment $1,043 - $689
17,222
kWh
$354
-
kW-mo/yr
- - -
02 2.7124: Make a practice of turning off lights when not needed $131 - $131
3,267
kWh
- - - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $383 $4 $203
5,062
kWh
$180
-
kW-mo/yr
- - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,458 $65 $1,785
44,615
kWh
$1,673
-
kW-mo/yr
- - -
05 2.7221: Lower temperature during the winter season and vice-versa $3,415 $130 $561
14,027
kWh
- - $2,854
-
MMBtu
-
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,221 $290 $630
15,763
kWh
$591
-
kW-mo/yr
- - -
07 2.2511: Insulate bare equipment $974 $203 - - - $974
-
MMBtu
-
08 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,534 $928 $2,534
63,360
kWh
- - - -
09 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $910 $416 $910
22,718
kWh
- - - -
10 4.812: Apply for investment incentives $238 $125 - - $238 - -
11 2.7135: Install occupancy sensors $3,393 $2,038 $3,393
84,819
kWh
- - - -
12 2.4221: Install compressor air intakes in coolest locations $519 $727 $268
6,700
kWh
$251
-
kW-mo/yr
- - -
13 3.4154: Eliminate leaks in water lines and valves $446 $1,250 - - - $247
-
MMBtu
$199
-
Tgal
14 2.3212: Optimize plant power factor $13,460 $43,320 - - $13,460 - -
15 2.7142: Utilize higher efficiency lamps and/or ballasts $5,680 $25,865 $2,931
73,277
kWh
$2,749
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $37,805 $75,361 $14,035
350,830
kWh
$5,798
-
kW-mo/yr
$13,698 $4,075
-
MMBtu
$199
-
Tgal
TOTAL IMPLEMENTED $18,718 $29,841 $9,431
235,768
kWh
$5,013
-
kW-mo/yr
- $4,075
-
MMBtu
$199
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs