| Assessment Year | 2016 |
|---|---|
| Principal Product | Ethanol |
| NAICS | 325110: Petrochemical Manufacturing |
| SIC | 2869: Industrial Organic Chemicals, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 39 |
| Plant Area |
123,479
ft2
|
| Annual Production | 50,000
Tgal
|
| Production Hrs. Annual | 8,640
hrs
|
| Location (State) | Indiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,637,983 | 33,974,489 |
kWh
|
$0.048 |
| Electricity Demand | $576,895 | 41,804 |
kW-mo/yr
|
$13.80 |
| Electricity Fees | $76,289 | - |
|
- |
| Natural Gas | $4,989,912 | 1,289,308 |
MMBtu
|
$3.87 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $53,436 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $14,417 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7261: Install timers and/or thermostats | $13,450 | $7 |
$2,293
47,712
kWh
|
- |
$11,157
-
MMBtu
|
|
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $967 | $22 |
$967
20,140
kWh
|
- | - | |
| 03 | 2.4323: Use optimum size and capacity equipment | $605 | - |
$436
9,067
kWh
|
$169
-
kW-mo/yr
|
- | |
| 04 | 2.7135: Install occupancy sensors | $19,981 | $2,354 |
$19,981
415,846
kWh
|
- | - | |
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $8,081 | $4,092 |
$7,821
162,778
kWh
|
$260
-
kW-mo/yr
|
- | |
| 06 | 2.7144: Install spectral reflectors / delamp | $1,743 | $2,278 |
$1,243
25,875
kWh
|
$500
-
kW-mo/yr
|
- | |
| 07 | 2.4131: Size electric motors for peak operating efficiency | $8,609 | $12,262 |
$8,354
166,219
kWh
|
$255
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $53,436 | $21,015 |
$41,095
847,637
kWh
|
$1,184
-
kW-mo/yr
|
$11,157
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $14,417 | $29 |
$3,260
67,852
kWh
|
- |
$11,157
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs