| Assessment Year | 2016 |
|---|---|
| Principal Product | Auto Parts and Accessories |
| NAICS | 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing |
| SIC | 3714: Motor Vehicle Parts and Accessories |
| Sales Range | $5 M to 10M |
| # of Employees | 47 |
| Plant Area |
250,000
ft2
|
| Annual Production | 632,022
pieces
|
| Production Hrs. Annual | 2,083
hrs
|
| Location (State) | Indiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $180,429 | 2,971,003 |
kWh
|
$0.061 |
| Electricity Demand | $67,061 | 11,575 |
kW-mo/yr
|
$5.79 |
| Electricity Fees | $1,800 | - |
|
- |
| Natural Gas | $111,247 | 17,279 |
MMBtu
|
$6.44 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $40,156 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,006 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,552 | - |
$1,001
16,477
kWh
|
$551
-
kW-mo/yr
|
- | - | |
| 02 | 4.821: Pay bills on time to avoid late fees | $560 | - | - | - | $560 | - | |
| 03 | 2.4323: Use optimum size and capacity equipment | $311 | - |
$274
4,513
kWh
|
$37
-
kW-mo/yr
|
- | - | |
| 04 | 2.2514: Cover open tanks | $3,767 | - | - | - | - |
$3,767
-
MMBtu
|
|
| 05 | 2.7224: Reduce space conditioning during non-working hours | $401 | $20 | - | - | - |
$401
-
MMBtu
|
|
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,020 | $115 |
$2,020
33,264
kWh
|
- | - | - | |
| 07 | 2.7135: Install occupancy sensors | $5,533 | $807 |
$5,533
91,116
kWh
|
- | - | - | |
| 08 | 2.2511: Insulate bare equipment | $3,328 | $604 | - | - | - |
$3,328
-
MMBtu
|
|
| 09 | 2.1233: Analyze flue gas for proper air/fuel ratio | $927 | $200 | - | - | - |
$927
-
MMBtu
|
|
| 10 | 2.432: Hardware | $747 | $260 |
$747
12,304
kWh
|
- | - | - | |
| 11 | 2.4221: Install compressor air intakes in coolest locations | $788 | $1,027 |
$577
9,499
kWh
|
$212
-
kW-mo/yr
|
- | - | |
| 12 | 2.4131: Size electric motors for peak operating efficiency | $5,971 | $8,516 |
$3,852
63,427
kWh
|
$2,119
-
kW-mo/yr
|
- | - | |
| 13 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $260 | $440 |
$260
4,380
kWh
|
- | - | - | |
| 14 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,183 | $7,207 |
$2,703
44,507
kWh
|
$1,480
-
kW-mo/yr
|
- | - | |
| 15 | 2.2437: Recover waste heat from equipment | $464 | $1,038 | - | - | - |
$464
-
MMBtu
|
|
| 16 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $190 | $664 |
$123
2,021
kWh
|
$68
-
kW-mo/yr
|
- | - | |
| 17 | 2.3192: Use fossil fuel powered generator during peak demand periods | $8,619 | $30,789 |
$4,464
73,500
kWh
|
$10,440
-
kW-mo/yr
|
- |
$(-6,285.0)
-
MMBtu
|
|
| 18 | 2.4133: Use most efficient type of electric motors | $534 | $2,607 |
$346
5,697
kWh
|
$188
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $40,156 | $54,294 |
$21,900
360,704
kWh
|
$15,095
-
kW-mo/yr
|
$560 |
$2,602
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $9,006 | $4,286 |
$3,496
57,666
kWh
|
$256
-
kW-mo/yr
|
$560 |
$4,694
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs