| Assessment Year | 2015 |
|---|---|
| Principal Product | Wastewater Treatment |
| NAICS | 221320: Sewage Treatment Facilities |
| SIC | 4952: Sewerage Systems |
| Sales Range | $1 M to 5M |
| # of Employees | 9 |
| Plant Area |
25,000
ft2
|
| Annual Production | 225,000
Tgal
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Indiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $120,935 | 2,863,600 |
kWh
|
$0.042 |
| Electricity Demand | $72,481 | 5,074 |
kW-mo/yr
|
$14.28 |
| Electricity Fees | $31,547 | - |
|
- |
| Natural Gas | $21,705 | 2,856 |
MMBtu
|
$7.60 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $28,335 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2211: Use optimum temperature | $3,192 | - | - | - | - |
$3,192
-
MMBtu
|
|
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $439 | - |
$439
8,678
kWh
|
- | - | - | |
| 03 | 2.4224: Upgrade controls on compressors | $2,318 | $1,216 |
$2,091
41,340
kWh
|
$227
-
kW-mo/yr
|
- | - | |
| 04 | 2.3212: Optimize plant power factor | $5,219 | $5,000 | - | - | $5,219 | - | |
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $14,286 | $16,000 |
$13,774
272,261
kWh
|
$512
-
kW-mo/yr
|
- | - | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $168 | $212 |
$100
1,985
kWh
|
$68
-
kW-mo/yr
|
- | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,713 | $6,999 |
$1,696
33,526
kWh
|
$1,017
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $28,335 | $29,427 |
$18,100
357,790
kWh
|
$1,824
-
kW-mo/yr
|
$5,219 |
$3,192
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs