Assessment Year | 2015 |
---|---|
Principal Product | plastic device components |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 125 |
Plant Area |
68,000
ft2
|
Annual Production | 70,000,000
pieces
|
Production Hrs. Annual | 5,900
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $216,389 | 5,314,114 |
kWh
|
$0.041 |
Electricity Demand | $265,155 | 11,319 |
kW-mo/yr
|
$23.43 |
Electricity Fees | $1,868 | - |
|
- |
Natural Gas | $14,741 | 1,623 |
MMBtu
|
$9.08 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $112,375 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 3.6192: Use a less expensive method of waste removal | $102,924 | - | - | - | - | - |
$102,924
-
lb
|
|
02 | 2.2211: Use optimum temperature | $1,853 | - | - | - |
$1,853
-
MMBtu
|
- | - | |
03 | 2.7135: Install occupancy sensors | $1,622 | $560 |
$1,622
40,259
kWh
|
- | - | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,492 | - |
$1,492
37,017
kWh
|
- | - | - | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,188 | - |
$544
13,511
kWh
|
$644
-
kW-mo/yr
|
- | - | - | |
06 | 2.2521: Isolate steam lines to avoid heating air conditioned areas | $61 | $19 |
$61
1,525
kWh
|
- | - | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,161 | $1,811 |
$532
13,205
kWh
|
$629
-
kW-mo/yr
|
- | - | - | |
08 | 2.4221: Install compressor air intakes in coolest locations | $1,780 | $1,780 |
$816
20,247
kWh
|
$964
-
kW-mo/yr
|
- | - | - | |
09 | 3.4115: Recover and reuse cooling water | $188 | $120 | - | - | - |
$188
-
gal
|
- | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $106 | $240 |
$106
2,628
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $112,375 | $4,530 |
$5,173
128,392
kWh
|
$2,237
-
kW-mo/yr
|
$1,853
-
MMBtu
|
$188
-
gal
|
$102,924
-
lb
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs