Assessment Year | 2014 |
---|---|
Principal Product | Injection Molding/Thermo Forming |
NAICS | 333249: Other Industrial Machinery Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 37 |
Plant Area |
80,000
ft2
|
Annual Production | 1,000,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $179,208 | 2,503,200 |
kWh
|
$0.072 |
Electricity Demand | $71,021 | 12,372 |
kW-mo/yr
|
$5.74 |
Electricity Fees | $23,561 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $37,598 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $18,710 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
---|---|---|---|---|---|---|---|
01 | 2.2511: Insulate bare equipment | $16,250 | - | - | - | $16,250 | |
02 | 4.812: Apply for investment incentives | $2,460 | $147 |
$2,460
36,885
kWh
|
- | - | |
03 | 2.7135: Install occupancy sensors | $1,916 | $284 |
$1,916
28,737
kWh
|
- | - | |
04 | 2.3212: Optimize plant power factor | $15,670 | $13,000 | - |
$15,670
-
kW-mo/yr
|
- | |
05 | 2.2511: Insulate bare equipment | $542 | $603 |
$542
8,121
kWh
|
- | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $479 | $1,050 |
$392
5,880
kWh
|
$87
-
kW-mo/yr
|
- | |
07 | 2.2511: Insulate bare equipment | $281 | $561 |
$281
4,343
kWh
|
- | - | |
TOTAL RECOMMENDED | $37,598 | $15,645 |
$5,591
83,966
kWh
|
$15,757
-
kW-mo/yr
|
$16,250 | ||
TOTAL IMPLEMENTED | $18,710 | $147 |
$2,460
36,885
kWh
|
- | $16,250 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs