ITAC Assessment: IP0024
ITAC logo
ITAC Assessment: IP0024
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Injection Molding/Thermo Forming
NAICS 333249: Other Industrial Machinery Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 37
Plant Area 80,000
ft2
Annual Production 1,000,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $179,208 2,503,200
kWh
Electricity Demand $71,021 12,372
kW-mo/yr
Electricity Fees $23,561 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $37,598 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $18,710

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.2511: Insulate bare equipment $16,250 - - - $16,250
02 4.812: Apply for investment incentives $2,460 $147 $2,460
36,885
kWh
- -
03 2.7135: Install occupancy sensors $1,916 $284 $1,916
28,737
kWh
- -
04 2.3212: Optimize plant power factor $15,670 $13,000 - $15,670
-
kW-mo/yr
-
05 2.2511: Insulate bare equipment $542 $603 $542
8,121
kWh
- -
06 2.4221: Install compressor air intakes in coolest locations $479 $1,050 $392
5,880
kWh
$87
-
kW-mo/yr
-
07 2.2511: Insulate bare equipment $281 $561 $281
4,343
kWh
- -
TOTAL RECOMMENDED $37,598 $15,645 $5,591
83,966
kWh
$15,757
-
kW-mo/yr
$16,250
TOTAL IMPLEMENTED $18,710 $147 $2,460
36,885
kWh
- $16,250
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs