Assessment Year | 2012 |
---|---|
Principal Product | Pneumatic, Hydraulic, and Electric Industrial Automation Actuators |
NAICS | 333995: Fluid Power Cylinder and Actuator Manufacturing |
SIC | 3593: Fluid Power Cylinders and Actuators |
Sales Range | $50 M to 100M |
# of Employees | 83 |
Plant Area |
83,000
ft2
|
Annual Production | 152,099
pieces
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $67,259 | 1,490,600 |
kWh
|
$0.045 |
Electricity Demand | $32,877 | 4,223 |
kW-mo/yr
|
$7.79 |
Electricity Fees | $38,537 | - |
|
- |
Natural Gas | $8,157 | 8,157 |
MMBtu
|
$1.00 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $47,621 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $30,659 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,520 | - |
$4,520
61,997
kWh
|
- | - | |
02 | 2.6231: Utilize controls to operate equipment only when needed | $2,343 | - |
$1,742
23,900
kWh
|
$601
-
kW-mo/yr
|
- | |
03 | 2.7221: Lower temperature during the winter season and vice-versa | $2,110 | - |
$2,110
28,949
kWh
|
- | - | |
04 | 2.7111: Reduce illumination to minimum necessary levels | $21,686 | $18,150 |
$16,382
280,682
kWh
|
$5,304
-
kW-mo/yr
|
- | |
05 | 2.7241: Install outside air damper / economizer on hvac unit | $6,462 | $15,867 |
$6,462
88,640
kWh
|
- | - | |
06 | 4.112: Replace old machine with new automatic multi-station tool | $10,500 | $27,000 | - | - | $10,500 | |
TOTAL RECOMMENDED | $47,621 | $61,017 |
$31,216
484,168
kWh
|
$5,905
-
kW-mo/yr
|
$10,500 | ||
TOTAL IMPLEMENTED | $30,659 | $18,150 |
$24,754
395,528
kWh
|
$5,905
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs