ITAC Assessment: IC0347
ITAC logo
ITAC Assessment: IC0347
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product Die Manufacturing for Doors
NAICS 321911: Wood Window and Door Manufacturing
SIC 2431: Millwork
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 450,000
ft2
Annual Production 500
units
Production Hrs. Annual 3,380
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $107,330 2,012,404
kWh
Electricity Demand $115,644 5,524
kW-mo/yr
Electricity Fees $24,181 -
Natural Gas $60,677 8,960
MMBtu
Other Gas $5,878 1
MMBtu
Waste Disposal Costs
Water Usage $5,779 509
Tgal
Water Disposal $5,775 523
Tgal
TOTAL YEARLY COSTS $325,264
RECOMMENDED SAVINGS* $12,715 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,908 $2,274 $1,417
26,730
kWh
$838
-
kW-mo/yr
$(-347.0)
-
MMBtu
02 2.2511: Insulate bare equipment $110 $193 $55
1,039
kWh
$55
-
kW-mo/yr
-
03 2.2136: Install / repair insulation on steam lines $1,674 $2,169 - - $1,674
-
MMBtu
04 2.2123: Insulate feedwater tank $184 $429 - - $184
-
MMBtu
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $4,275 $747 $1,513
28,548
kWh
$2,762
-
kW-mo/yr
-
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,490 $400 $1,436
27,097
kWh
$1,054
-
kW-mo/yr
-
07 2.4221: Install compressor air intakes in coolest locations $651 $760 $223
4,206
kWh
$428
-
kW-mo/yr
-
08 2.6231: Utilize controls to operate equipment only when needed $168 $1,060 $14
265
kWh
$154
-
kW-mo/yr
-
09 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $119 - $51
960
kWh
$68
-
kW-mo/yr
-
10 2.4323: Use optimum size and capacity equipment $94 $507 $40
761
kWh
$54
-
kW-mo/yr
-
11 2.3132: Recharge batteries on during off-peak demand periods $333 - - $333
-
kW-mo/yr
-
12 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $465 $251 $192
3,628
kWh
$272
-
kW-mo/yr
-
13 2.4239: Eliminate or reduce compressed air usage $245 - $24
447
kWh
$221
-
kW-mo/yr
-
TOTAL RECOMMENDED $12,715 $8,790 $4,965
93,679
kWh
$6,240
-
kW-mo/yr
$1,511
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs