ITAC Assessment: IC0283
ITAC logo
ITAC Assessment: IC0283
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Dry Mix Concrete
NAICS 327320: Ready-Mix Concrete Manufacturing
SIC 3273: Ready-Mixed Concrete
Sales Range $10
M
to 50
M
# of Employees 25
Plant Area 380,000
ft2
Annual Production 168,000
ton
Production Hrs. Annual 2,808
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $77,139 448,866
kWh
Electricity Fees $1,838 -
Natural Gas $95,521 25,761
MMBtu
Waste Disposal Costs
Water Usage $26,109 5,928
Tgal
TOTAL YEARLY COSTS $200,607
RECOMMENDED SAVINGS* $2,445 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $654

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2511: Insulate bare equipment $112 $886 - $112
-
MMBtu
02 2.2136: Install / repair insulation on steam lines $192 $13 - $192
-
MMBtu
03 2.2414: Use waste heat from hot flue gases to preheat $1,791 $4,650 - $1,791
-
MMBtu
04 2.4221: Install compressor air intakes in coolest locations $350 $840 $350
2,034
kWh
-
TOTAL RECOMMENDED $2,445 $6,389 $350
2,034
kWh
$2,095
-
MMBtu
TOTAL IMPLEMENTED $654 $1,739 $350
2,034
kWh
$304
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs