Assessment Year | 2023 |
---|---|
Principal Product | Dry Mix Concrete |
NAICS | 327320: Ready-Mix Concrete Manufacturing |
SIC | 3273: Ready-Mixed Concrete |
Sales Range | $10 M to 50M |
# of Employees | 25 |
Plant Area |
380,000
ft2
|
Annual Production | 168,000
ton
|
Production Hrs. Annual | 2,808
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $77,139 | 448,866 |
kWh
|
$0.17 | |
Electricity Fees | $1,838 | - |
|
- | |
Natural Gas | $95,521 | 25,761 |
MMBtu
|
$3.71 | |
Waste Disposal Costs | |||||
Water Usage | $26,109 | 5,928 |
Tgal
|
$4.40 | |
TOTAL YEARLY COSTS | $200,607 | ||||
RECOMMENDED SAVINGS* | $2,445 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $654 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.2511: Insulate bare equipment | $112 | $886 | - |
$112
-
MMBtu
|
|
02 | 2.2136: Install / repair insulation on steam lines | $192 | $13 | - |
$192
-
MMBtu
|
|
03 | 2.2414: Use waste heat from hot flue gases to preheat | $1,791 | $4,650 | - |
$1,791
-
MMBtu
|
|
04 | 2.4221: Install compressor air intakes in coolest locations | $350 | $840 |
$350
2,034
kWh
|
- | |
TOTAL RECOMMENDED | $2,445 | $6,389 |
$350
2,034
kWh
|
$2,095
-
MMBtu
|
||
TOTAL IMPLEMENTED | $654 | $1,739 |
$350
2,034
kWh
|
$304
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs