Assessment Year | 2020 |
---|---|
Principal Product | Forged Metal Products |
NAICS | 331110: Iron and Steel Mills and Ferroalloy Manufacturing |
SIC | 3312: Steel Works, Blast Furnaces (Including Coke Ovens), and Rolling Mills |
Sales Range | $10 M to 50M |
# of Employees | 75 |
Plant Area |
117,000
ft2
|
Annual Production | 1,500,000
lb
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $79,326 | 1,192,081 |
kWh
|
$0.067 | |
Electricity Demand | $22,207 | 3,084 |
kW-mo/yr
|
$7.20 | |
Electricity Fees | $7,726 | - |
|
- | |
Natural Gas | $5,992 | 5,025 |
MMBtu
|
$1.19 | |
Waste Disposal Costs | |||||
Water Usage | $2,558 | 530 |
Tgal
|
$4.82 | |
TOTAL YEARLY COSTS | $117,809 | ||||
RECOMMENDED SAVINGS* | $13,221 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $13,221 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,669 | $32,097 |
$2,077
29,676
kWh
|
$592
-
kW-mo/yr
|
|
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,418 | $1,107 |
$2,308
32,974
kWh
|
$110
-
kW-mo/yr
|
|
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,059 | $3,380 |
$4,962
70,882
kWh
|
$1,097
-
kW-mo/yr
|
|
04 | 2.4221: Install compressor air intakes in coolest locations | $2,075 | $3,800 |
$1,976
28,224
kWh
|
$100
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $13,221 | $40,384 |
$11,323
161,756
kWh
|
$1,899
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $13,221 | $40,384 |
$11,323
161,756
kWh
|
$1,899
-
kW-mo/yr
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs