ITAC Assessment: AR0008
ITAC logo
ITAC Assessment: AR0008
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Aircraft Assemblies
NAICS
n/a
SIC 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 97,000
ft2
Annual Production 42
pieces
Production Hrs. Annual 2,086
hrs
Location (State) Arkansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $159,836 2,064,478
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $18,592 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,102

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,296 $1,589 $1,296
16,706
kWh
02 2.7111: Reduce illumination to minimum necessary levels $13,930 $6,240 $13,930
179,953
kWh
03 2.7245: Use direct air supply to exhaust hoods $1,379 $1,000 $1,379
17,878
kWh
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,102 $130 $1,102
14,361
kWh
05 2.4221: Install compressor air intakes in coolest locations $885 $100 $885
11,430
kWh
TOTAL RECOMMENDED $18,592 $9,059 $18,592
240,328
kWh
TOTAL IMPLEMENTED $1,102 $130 $1,102
14,361
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs