Assessment Year | 2018 |
---|---|
Principal Product | Wastewater Treatment Facility |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | less than $500 k |
# of Employees | 22 |
Plant Area |
50,000
ft2
|
Annual Production | 153,000
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $419,574 | 5,304,800 |
kWh
|
$0.079 |
Natural Gas | $44,705 | 7,787 |
MMBtu
|
$5.74 |
TOTAL YEARLY COSTS | $464,279 | |||
RECOMMENDED SAVINGS* | $52,498 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $34,484 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
---|---|---|---|---|---|
01 | 2.4226: Use / purchase optimum sized compressor | $26,150 | $285,000 |
$26,150
326,871
kWh
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,334 | $12,088 |
$8,334
104,174
kWh
|
|
03 | 2.4133: Use most efficient type of electric motors | $18,014 | $22,842 |
$18,014
225,169
kWh
|
|
TOTAL RECOMMENDED | $52,498 | $319,930 |
$52,498
656,214
kWh
|
||
TOTAL IMPLEMENTED | $34,484 | $297,088 |
$34,484
431,045
kWh
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs