ITAC Assessment: IC0169
ITAC logo
ITAC Assessment: IC0169
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product slit stainless steel
NAICS 331513: Steel Foundries (except Investment)
SIC 3312: Steel Works, Blast Furnaces (Including Coke Ovens), and Rolling Mills
Sales Range $10
M
to 50
M
# of Employees 37
Plant Area 39,000
ft2
Annual Production 12,500
ton
Production Hrs. Annual 4,267
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $38,000 469,081
kWh
Electricity Demand $10,648 1,943
kW-mo/yr
Electricity Fees $8,268 -
Natural Gas $43,245 3,133
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $74,469 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,717 $6,357 $1,320
16,287
kWh
$388
-
kW-mo/yr
- $51 - $(-42.0)
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,298 $1,317 $976
12,070
kWh
$322
-
kW-mo/yr
- - - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $863 $71 $726
8,960
kWh
$137
-
kW-mo/yr
- - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $127 $99 $55
683
kWh
$5
-
kW-mo/yr
- $23 $44 -
05 2.6212: Turn off equipment during breaks, reduce operating time $20,393 $5,249 $20,075
247,841
kWh
$318
-
kW-mo/yr
- - - -
06 2.4133: Use most efficient type of electric motors $1,108 $1,339 $928
11,446
kWh
$180
-
kW-mo/yr
- - - -
07 2.7224: Reduce space conditioning during non-working hours $538 - - - $538
-
MMBtu
- - -
08 2.7447: Install vinyl strip / high speed / air curtain doors $5,189 $1,632 - - $5,189
-
MMBtu
- - -
09 2.7447: Install vinyl strip / high speed / air curtain doors $4,975 $4,551 $(-185.0)
(-2,270)
kWh
$(-29.0)
-
kW-mo/yr
$5,189
-
MMBtu
- - -
10 2.7231: Use radiant heater for spot heating $28,097 $1,670 - - $28,097
-
MMBtu
- - -
11 2.2136: Install / repair insulation on steam lines $318 $613 - - $318
-
MMBtu
- - -
12 2.7232: Replace existing hvac unit with high efficiency model $5,403 $2,401 $38
465
kWh
$11
-
kW-mo/yr
$5,354
-
MMBtu
- - -
13 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,074 $1,265 $4,074
50,294
kWh
- - - - -
14 2.7313: Recycle air for heating, ventilation and air conditioning $124 $600 - - $124
-
MMBtu
- - -
15 2.6211: Conserve energy by efficient use of vending machines $245 - $146
1,800
kWh
$99
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $74,469 $27,164 $28,153
347,576
kWh
$1,431
-
kW-mo/yr
$44,809
-
MMBtu
$74 $44 $(-42.0)
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs