ITAC Assessment: IC0163
ITAC logo
ITAC Assessment: IC0163
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2009
Principal Product ASME Code Pressure Vessels
NAICS 332420: Metal Tank (Heavy Gauge) Manufacturing
SIC 3324: Steel Investment Foundries
Sales Range $5
M
to 10
M
# of Employees 45
Plant Area 145,000
ft2
Annual Production 2,500
pieces
Production Hrs. Annual 2,625
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $57,602 1,610,600
kWh
Electricity Demand $77,525 7,146
kW-mo/yr
Natural Gas $187,074 16,985
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,715,229 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,703,139

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $528 $332 $82
2,269
kWh
$33
-
kW-mo/yr
- - $91 - $322 -
02 2.7135: Install occupancy sensors $635 $538 $255
7,101
kWh
$380
-
kW-mo/yr
- - - - - -
03 2.2443: Re-use or recycle hot or cold process exhaust air $3,314 $102 - - $3,314
-
MMBtu
- - - - -
04 2.4231: Reduce the pressure of compressed air to the minimum required $357 - $357
9,920
kWh
- - - - - - -
05 2.4239: Eliminate or reduce compressed air usage $2,247 - $554
15,390
kWh
$1,693
-
kW-mo/yr
- - - - - -
06 2.7231: Use radiant heater for spot heating $9,226 $39,560 - - $9,226
-
MMBtu
- - - - -
07 2.2442: Preheat combustion air with waste heat $6,925 $17,000 - - $6,925
-
MMBtu
- - - - -
08 3.5131: Recycle white water $2,034 $771 $(-779.0)
21,630
kWh
- - $2,813
-
Tgal
- - - -
09 2.6211: Conserve energy by efficient use of vending machines $260 - $65
1,800
kWh
$195
-
kW-mo/yr
- - - - - -
10 4.111: Add equipment/ operators to reduce production bottleneck $1,689,703 - - - - - $(-72,509.0) $(-1,572,000.0) - $3,334,212
TOTAL RECOMMENDED $1,715,229 $58,303 $534
58,110
kWh
$2,301
-
kW-mo/yr
$19,465
-
MMBtu
$2,813
-
Tgal
$(-72,418.0) $(-1,572,000.0) $322 $3,334,212
TOTAL IMPLEMENTED $1,703,139 $18,743 $(-442.0)
31,000
kWh
$413
-
kW-mo/yr
$10,239
-
MMBtu
$2,813
-
Tgal
$(-72,418.0) $(-1,572,000.0) $322 $3,334,212
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs