Assessment Year | 2008 |
---|---|
Principal Product | Ball Bearings |
NAICS | 333613: Mechanical Power Transmission Equipment Manufacturing |
SIC | 3562: Ball and Roller Bearings |
Sales Range | $100 M to 500M |
# of Employees | 192 |
Plant Area |
158,137
ft2
|
Annual Production | 300,000,000
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $525,761 | 10,027,860 |
kWh
|
$0.052 |
Electricity Demand | $191,380 | 20,005 |
kW-mo/yr
|
$9.57 |
Natural Gas | $233,229 | 25,351 |
MMBtu
|
$9.20 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $58,456 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,573 | $4,032 |
$1,119
21,510
kWh
|
$641
-
kW-mo/yr
|
- | $210 | $(-397.0) | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $540 | $1,133 |
$260
4,992
kWh
|
$278
-
kW-mo/yr
|
- | $(-5.0) | $7 | |
03 | 2.7124: Make a practice of turning off lights when not needed | $12,321 | - |
$3,985
76,632
kWh
|
$8,336
-
kW-mo/yr
|
- | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,900 | $1,940 |
$409
7,858
kWh
|
$105
-
kW-mo/yr
|
- | $591 | $795 | |
05 | 2.4133: Use most efficient type of electric motors | $1,785 | $2,728 |
$1,431
27,498
kWh
|
$354
-
kW-mo/yr
|
- | - | - | |
06 | 2.4226: Use / purchase optimum sized compressor | $6,146 | $80,600 |
$6,146
118,189
kWh
|
- | - | - | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,093 | $5,980 |
$3,093
59,452
kWh
|
- | - | - | - | |
08 | 2.2515: Use optimum thickness insulation | $19,374 | $4,100 | - | - |
$19,374
-
MMBtu
|
- | - | |
09 | 2.6212: Turn off equipment during breaks, reduce operating time | $135 | - |
$68
1,314
kWh
|
$67
-
kW-mo/yr
|
- | - | - | |
10 | 2.4322: Use or replace with energy efficient substitutes | $1,616 | - |
$468
9,000
kWh
|
$1,148
-
kW-mo/yr
|
- | - | - | |
11 | 2.8113: Purchase gas directly from a contract gas supplier | $9,973 | - | - | - |
$9,973
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $58,456 | $100,513 |
$16,979
326,445
kWh
|
$10,929
-
kW-mo/yr
|
$29,347
-
MMBtu
|
$796 | $405 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs