Assessment Year | 2008 |
---|---|
Principal Product | Automotive Fasteners |
NAICS | 332722: Bolt, Nut, Screw, Rivet, and Washer Manufacturing |
SIC | 3452: Bolts, Nuts, Screws, Rivets, and Washers |
Sales Range | $10 M to 50M |
# of Employees | 152 |
Plant Area |
141,106
ft2
|
Annual Production | 240,000,000
pieces
|
Production Hrs. Annual | 6,600
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $153,052 | 5,789,938 |
kWh
|
$0.026 |
Electricity Demand | $214,396 | 18,104 |
kW-mo/yr
|
$11.84 |
Natural Gas | $163,082 | 17,599 |
MMBtu
|
$9.27 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $70,836 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $29,939 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,308 | $2,645 |
$2,308
88,624
kWh
|
- | - | - | - | - | |
02 | 2.4239: Eliminate or reduce compressed air usage | $1,407 | $3,105 |
$768
29,542
kWh
|
$639
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.4224: Upgrade controls on compressors | $22,414 | $12,440 |
$3,518
135,300
kWh
|
$18,896
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,435 | $15,346 |
$1,542
59,253
kWh
|
$2,241
-
kW-mo/yr
|
- | - | - | $652 | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $811 | $211 |
$227
8,732
kWh
|
$189
-
kW-mo/yr
|
- | - | $388 | $7 | |
06 | 2.7135: Install occupancy sensors | $1,834 | $4,703 |
$837
32,107
kWh
|
$997
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $19,058 | $103,849 |
$11,338
436,062
kWh
|
$9,389
-
kW-mo/yr
|
- | - | $(-48.0) | $(-1,621.0) | |
08 | 2.4133: Use most efficient type of electric motors | $2,303 | $6,227 |
$1,096
42,128
kWh
|
$1,207
-
kW-mo/yr
|
- | - | - | - | |
09 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $92 | $269 |
$21
800
kWh
|
$71
-
kW-mo/yr
|
- | - | - | - | |
10 | 2.2511: Insulate bare equipment | $2,623 | $1,416 | - | - |
$2,623
-
MMBtu
|
- | - | - | |
11 | 2.1333: Convert combustion equipment to burn oil | $7,860 | $23,865 | - | - |
$6,804
-
MMBtu
|
$1,056
-
gal
|
- | - | |
12 | 2.7221: Lower temperature during the winter season and vice-versa | $4,079 | - | - | - |
$4,079
-
MMBtu
|
- | - | - | |
13 | 2.6211: Conserve energy by efficient use of vending machines | $779 | - |
$140
5,400
kWh
|
$639
-
kW-mo/yr
|
- | - | - | - | |
14 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $833 | $231 |
$173
6,658
kWh
|
$107
-
kW-mo/yr
|
- | - | $293 | $260 | |
TOTAL RECOMMENDED | $70,836 | $174,307 |
$21,968
844,606
kWh
|
$34,375
-
kW-mo/yr
|
$13,506
-
MMBtu
|
$1,056
-
gal
|
$633 | $(-702.0) | ||
TOTAL IMPLEMENTED | $29,939 | $17,374 |
$4,668
179,465
kWh
|
$20,639
-
kW-mo/yr
|
$4,079
-
MMBtu
|
- | $293 | $260 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs