ITAC Assessment: IC0125
ITAC logo
ITAC Assessment: IC0125
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2007
Principal Product sorbitol and maltitol
NAICS 311930: Flavoring Syrup and Concentrate Manufacturing
SIC 2869: Industrial Organic Chemicals, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 41
Plant Area 93,500
ft2
Annual Production 70,000
ton
Production Hrs. Annual 8,736
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,395,650 24,443,365
kWh
Electricity Demand $191,513 40,798
kW-mo/yr
Natural Gas $2,603,188 282,677
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $899,372 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $87,197

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Ancillary Material Cost Savings
01 2.2437: Recover waste heat from equipment $202,850 $475,200 $22,123
388,110
kWh
$2,459
-
kW-mo/yr
$178,268
-
MMBtu
- -
02 2.2437: Recover waste heat from equipment $305,019 $900,000 - - $293,046
-
MMBtu
$11,973
-
Tgal
-
03 2.3321: Use steam pressure reduction to generate power $227,690 $372,000 $227,690
3,994,560
kWh
- - - -
04 2.2163: Use minimum steam operating pressure $611 - - - $494
-
MMBtu
$117
-
Tgal
-
05 2.8114: Change rate schedules or other changes in utility service $36,000 - $36,000
-
kWh
- - - -
06 2.2614: Use cooling tower or economizer to replace chiller cooling $21,910 $4,260 $19,943
349,867
kWh
$1,967
-
kW-mo/yr
- - -
07 2.1233: Analyze flue gas for proper air/fuel ratio $25,485 $4,800 - - $25,485
-
MMBtu
- -
08 2.4224: Upgrade controls on compressors $12,731 $18,755 $11,453
200,928
kWh
$1,278
-
kW-mo/yr
- - -
09 2.5111: Convert from indirect to direct fired systems $52,577 $43,780 - - $38,726
-
MMBtu
$13,851
-
Tgal
-
10 2.4323: Use optimum size and capacity equipment $5,975 $14,767 $5,975
104,832
kWh
- - - -
11 2.4133: Use most efficient type of electric motors $6,961 $16,278 $6,073
106,587
kWh
$888
-
kW-mo/yr
- - -
12 2.6127: Maintain air filters by cleaning or replacement $1,563 - $2,667
46,803
kWh
$296
-
kW-mo/yr
- - $(-1,400.0)
TOTAL RECOMMENDED $899,372 $1,849,840 $331,924
5,191,687
kWh
$6,888
-
kW-mo/yr
$536,019
-
MMBtu
$25,941
-
Tgal
$(-1,400.0)
TOTAL IMPLEMENTED $87,197 $64,858 $8,740
153,390
kWh
$1,184
-
kW-mo/yr
$64,705
-
MMBtu
$13,968
-
Tgal
$(-1,400.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs