ITAC Assessment: IC0111
ITAC logo
ITAC Assessment: IC0111
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product sodium and calcium phosphates
NAICS 325180: Other Basic Inorganic Chemical Manufacturing
SIC 2819: Industrial Inorganic Chemicals, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 170
Plant Area 863,656
ft2
Annual Production 172,004,786
lb
Production Hrs. Annual 8,520
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $2,245,332 55,775,718
kWh
Electricity Demand $383,116 85,899
kW-mo/yr
Electricity Fees $575,799 -
Natural Gas $4,489,444 648,918
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,522,594 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,172,759

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (non-haz) Savings Ancillary Material Cost Savings
01 2.1394: Replace steam jets on vacuum system with electric motor driven vacuum pumps $803,012 $258,000 $(-44,148.0)
959,729
kWh
$(-8,840.0)
-
kW-mo/yr
$806,000
-
MMBtu
$50,000
-
Tgal
- -
02 2.3411: Replace electric motors with back pressure steam turbines and use exhaust steam for process heat $95,000 $442,680 $238,000
4,572,720
kWh
- $(-138,000.0)
-
MMBtu
$(-5,000.0)
-
Tgal
- -
03 2.5111: Convert from indirect to direct fired systems $186,788 $135,156 - - $164,788
-
MMBtu
$22,000
-
Tgal
- -
04 2.2121: Increase amount of condensate returned $93,000 $235,998 - - $34,000
-
MMBtu
$59,000
-
Tgal
- -
05 2.6231: Utilize controls to operate equipment only when needed $11,047 $30,000 - - $7,547
-
MMBtu
- - $3,500
06 2.1243: Use heat from boiler blowdown to preheat boiler feed water $57,000 $36,000 - - $55,000
-
MMBtu
$2,000
-
Tgal
- -
07 2.2163: Use minimum steam operating pressure $22,776 - - - $22,776
-
MMBtu
- - -
08 2.2135: Repair and eliminate steam leaks $9,304 $2,800 - - - - $9,304
-
gal
-
09 2.2113: Repair or replace steam traps $158,427 $5,152 - - $158,427
-
MMBtu
- - -
10 2.2136: Install / repair insulation on steam lines $17,406 $19,704 - - $17,406
-
MMBtu
- - -
11 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $23,163 $1,600 $20,442
444,378
kWh
$2,721
-
kW-mo/yr
- - - -
12 2.4133: Use most efficient type of electric motors $45,671 $195,432 $40,210
874,042
kWh
$5,461
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $1,522,594 $1,362,522 $254,504
6,850,869
kWh
$(-658.0)
-
kW-mo/yr
$1,127,944
-
MMBtu
$128,000
-
Tgal
$9,304
-
gal
$3,500
TOTAL IMPLEMENTED $1,172,759 $718,686 $16,504
2,278,149
kWh
$(-658.0)
-
kW-mo/yr
$1,038,609
-
MMBtu
$109,000
-
Tgal
$9,304
-
gal
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (non-haz) Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs