ITAC Assessment: IC0104
ITAC logo
ITAC Assessment: IC0104
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Forged Spur Gear Blanks and Forged Net Bevel Gears
NAICS 332111: Iron and Steel Forging
SIC 3246:
Sales Range $10
M
to 50
M
# of Employees 105
Plant Area 164,855
ft2
Annual Production 4,200,000
pieces
Production Hrs. Annual 7,416
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,142,380 20,927,390
kWh
Electricity Demand $466,228 55,376
kW-mo/yr
Electricity Fees $5,556 -
Natural Gas $179,371 22,134
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $114,995 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $96,070

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7221: Lower temperature during the winter season and vice-versa $25,653 $1,200 - - $25,653
-
MMBtu
- -
02 2.7224: Reduce space conditioning during non-working hours $1,264 $100 - - $1,264
-
MMBtu
- -
03 2.3191: Use demand controller or load shedder $18,925 $50,000 - $18,925
-
kW-mo/yr
- - -
04 2.4133: Use most efficient type of electric motors $22,421 $119,810 $17,967
326,521
kWh
$4,454
-
kW-mo/yr
- - -
05 2.6218: Turn off equipment when not in use $2,110 - $1,688
30,676
kWh
$422
-
kW-mo/yr
- - -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $13,948 $2,100 $12,412
225,722
kWh
$1,536
-
kW-mo/yr
- - -
07 2.4231: Reduce the pressure of compressed air to the minimum required $1,510 - $1,207
21,947
kWh
$303
-
kW-mo/yr
- - -
08 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $24,843 $107,641 $19,571
355,815
kWh
$5,272
-
kW-mo/yr
- - -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $3,662 $13,166 $1,989
36,159
kWh
$993
-
kW-mo/yr
- $112 $568
10 2.7142: Utilize higher efficiency lamps and/or ballasts $659 $800 $303
5,505
kWh
$67
-
kW-mo/yr
- $92 $197
TOTAL RECOMMENDED $114,995 $294,817 $55,137
1,002,345
kWh
$31,972
-
kW-mo/yr
$26,917
-
MMBtu
$204 $765
TOTAL IMPLEMENTED $96,070 $244,817 $55,137
1,002,345
kWh
$13,047
-
kW-mo/yr
$26,917
-
MMBtu
$204 $765
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs