ITAC Assessment: CO0711
ITAC logo
ITAC Assessment: CO0711
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Contract Machined Metal Parts
NAICS 332710: Machine Shops
SIC 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 85
Plant Area 41,200
ft2
Annual Production 1,000,000
pieces
Production Hrs. Annual 5,300
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $62,248 1,427,040
kWh
Electricity Demand $113,849 5,430
kW-mo/yr
Electricity Fees $1,180 -
Natural Gas $13,516 2,301
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $13,570 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $7,360 $620 $3,340
82,200
kWh
$4,020
-
kW-mo/yr
- - -
02 2.2511: Insulate bare equipment $900 $960 - - $900
-
MMBtu
- -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $350 $340 $160
4,000
kWh
$190
-
kW-mo/yr
- - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $4,960 $15,540 $1,700
41,800
kWh
$2,840
-
kW-mo/yr
- $130 $290
TOTAL RECOMMENDED $13,570 $17,460 $5,200
128,000
kWh
$7,050
-
kW-mo/yr
$900
-
MMBtu
$130 $290
TOTAL IMPLEMENTED - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs