Assessment Year | 2015 |
---|---|
Principal Product | Contract Machined Metal Parts |
NAICS | 332710: Machine Shops |
SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 85 |
Plant Area |
41,200
ft2
|
Annual Production | 1,000,000
pieces
|
Production Hrs. Annual | 5,300
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $62,248 | 1,427,040 |
kWh
|
$0.044 |
Electricity Demand | $113,849 | 5,430 |
kW-mo/yr
|
$20.97 |
Electricity Fees | $1,180 | - |
|
- |
Natural Gas | $13,516 | 2,301 |
MMBtu
|
$5.87 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $13,570 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,360 | $620 |
$3,340
82,200
kWh
|
$4,020
-
kW-mo/yr
|
- | - | - | |
02 | 2.2511: Insulate bare equipment | $900 | $960 | - | - |
$900
-
MMBtu
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $350 | $340 |
$160
4,000
kWh
|
$190
-
kW-mo/yr
|
- | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,960 | $15,540 |
$1,700
41,800
kWh
|
$2,840
-
kW-mo/yr
|
- | $130 | $290 | |
TOTAL RECOMMENDED | $13,570 | $17,460 |
$5,200
128,000
kWh
|
$7,050
-
kW-mo/yr
|
$900
-
MMBtu
|
$130 | $290 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs