Assessment Year | 2003 |
---|---|
Principal Product | Respiratory and Opthalmic Prescripion Pharmaceuticals |
NAICS | 325412: Pharmaceutical Preparation Manufacturing |
SIC | 2834: Pharmaceutical Preparations |
Sales Range | $100 M to 500M |
# of Employees | 700 |
Plant Area |
150,000
ft2
|
Annual Production | 50,000,000
pieces
|
Production Hrs. Annual | 6,120
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $522,248 | 15,598,531 |
kWh
|
$0.033 |
Electricity Demand | $414,023 | 29,195 |
kW-mo/yr
|
$14.18 |
Electricity Fees | $72,263 | - |
|
- |
Natural Gas | $207,069 | 30,857 |
MMBtu
|
$6.71 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $59,507 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,384 | $3,000 |
$6,548
116,921
kWh
|
$836
-
kW-mo/yr
|
- | - | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $1,075 | $3,136 |
$953
17,012
kWh
|
$122
-
kW-mo/yr
|
- | - | - | |
03 | 2.4133: Use most efficient type of electric motors | $3,765 | $1,840 |
$3,338
39,736
kWh
|
$427
-
kW-mo/yr
|
- | - | - | |
04 | 2.2136: Install / repair insulation on steam lines | $2,181 | $1,832 | - | - |
$2,181
-
MMBtu
|
- | - | |
05 | 2.2136: Install / repair insulation on steam lines | $446 | $792 | - | - |
$446
-
MMBtu
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $22,696 | $89,463 |
$16,160
288,582
kWh
|
$2,065
-
kW-mo/yr
|
- | $121 | $4,350 | |
07 | 2.7135: Install occupancy sensors | $6,054 | $12,848 |
$5,900
103,557
kWh
|
$154
-
kW-mo/yr
|
- | - | - | |
08 | 2.7243: Improve air circulation with destratification fans / other methods | $15,906 | $39,257 |
$(-1,113.0)
(-19,877)
kWh
|
$(-274.0)
-
kW-mo/yr
|
$16,663
-
MMBtu
|
$630 | - | |
TOTAL RECOMMENDED | $59,507 | $152,168 |
$31,786
545,931
kWh
|
$3,330
-
kW-mo/yr
|
$19,290
-
MMBtu
|
$751 | $4,350 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs