ITAC Assessment: IC0054
ITAC logo
ITAC Assessment: IC0054
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Cast Polyurethane Parts
NAICS 326299: All Other Rubber Product Manufacturing
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 75
Plant Area 50,000
ft2
Annual Production 400,000
lb
Production Hrs. Annual 5,464
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $38,934 1,106,640
kWh
Electricity Demand $31,775 2,596
kW-mo/yr
Electricity Fees $4,641 -
Natural Gas $62,838 9,585
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $11,705 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $358

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.4322: Use or replace with energy efficient substitutes $358 $1,074 $205
5,707
kWh
$153
-
kW-mo/yr
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,888 $7,452 $1,264
35,112
kWh
$942
-
kW-mo/yr
$(-266.0) $(-52.0)
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,471 $1,000 $839
23,355
kWh
$632
-
kW-mo/yr
- -
04 2.7135: Install occupancy sensors $808 $2,002 $428
11,884
kWh
$380
-
kW-mo/yr
- -
05 2.4221: Install compressor air intakes in coolest locations $192 $150 $76
2,114
kWh
$116
-
kW-mo/yr
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $6,988 $19,296 $3,175
88,173
kWh
$2,371
-
kW-mo/yr
$142 $1,300
TOTAL RECOMMENDED $11,705 $30,974 $5,987
166,345
kWh
$4,594
-
kW-mo/yr
$(-124.0) $1,248
TOTAL IMPLEMENTED $358 $1,074 $205
5,707
kWh
$153
-
kW-mo/yr
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs